Prospect Highway Upgrade
How do you install sophisticated electrical ventilation systems along an active highway without disrupting traffic? This was the challenge we faced during the $280 million Prospect Highway upgrade. Our Level 2 certified team had to meet exacting government specifications while working in exposed roadside conditions. We began with thorough hazard reduction protocols before implementing weatherproof electrical infrastructure designed specifically for harsh roadside environments. By taking full responsibility for compliance documentation and testing, we ensured that every aspect met Transport, Roads, and Maritime Services standards. The project showcased our expertise in transportation infrastructure, delivering zero safety incidents over the 6-month project while creating systems that continue to perform reliably with minimal maintenance.

Client: Austream Builders for Transport Roads and Maritime Services
Location: Western Sydney, NSW
Industry: Transport Infrastructure
Project Value: Part of $280 Million project

Challenge
The Prospect Highway upgrade required sophisticated electrical systems for ventilation as part of the noise attenuation works. Specific challenges included:
- Working in active transport corridors with minimal disruption to traffic
- Meeting exacting government specifications for safety and performance
- Coordinating with multiple contractors and stakeholders
- Completing hazard reduction works before installation could commence
- Ensuring all systems would perform reliably in a harsh roadside environment
Our Solution
Beaches Electric delivered a complete end-to-end solution:

Compliance Management:
- Took responsibility for all electrical compliance documentation
- Conducted comprehensive testing of all installed systems
- Provided detailed handover documentation and training for maintenance personnel

Hazard Management:
- Conducted thorough site assessment to identify and document all potential hazards
- Implemented detailed hazard reduction protocols before installation work began
- Maintained continuous monitoring throughout the project

Technical Implementation:
- Supplied, wired and installed complete ventilation systems for noise attenuation
- Incorporated weatherproof electrical infrastructure designed for roadside conditions
- Implemented energy-efficient controls to minimise ongoing operational costs

Results
- Achieved zero safety and compliance issues throughout the 6-month project duration
- Completed all electrical work on schedule, supporting the broader project timeline
- Delivered systems that met or exceeded all performance specifications
- Established Beaches Electric as a trusted contractor for RMS projects
- Created electrical infrastructure that continues to perform reliably with minimal maintenance

Team Expertise Applied
This project showcased our expertise in:
- Transportation infrastructure electrical requirements
- Level 2 electrical work for roadside applications
- Integration of ventilation system electrical components
- Government compliance and documentation
- Hazard management in active transport corridors.